East ElkhartTransmission Line Project


Indiana Michigan Power representatives plan power grid upgrades to improve electric reliability and efficiency for customers in north-central Indiana.

The East Elkhart Transmission Line Project involves:

  • Building about 2 miles of power line to connect the proposed RV Capital Substation, off County Road 19, to an existing power pole near County Road 23.
  • Rebuilding about 1 mile of power line between County Road 23 and County Road 123.
  • Removing about 2 miles of power line between County Road 23 and County Road 19.

The existing 60-year-old power line consists of aging equipment that does not meet today's operational standards. In the past decade, the existing power line has experienced five service interruptions resulting in extended power outages for area customers. The planned improvements provide a new power source to strengthen the local electric power grid, provide power to a future customer in the area and support economic development.

Company officials expect construction to begin summer 2024 and conclude spring 2025.

Project Updates

February 2023: I&M representatives announced the final proposed route for this project. Feedback provided by the community helped determine this route.

November 2022: I&M representatives announced the East Elkhart Transmission Line Project and hosted an in-person open house on December 7th to gather feedback from landowners and community members about possible route options for the new transmission line. Company representatives also hosted a virtual open house for community members to learn more about the project and share input.

Timeline

 
Project Timeline
 

Structures

Structure

This project involves installing steel poles.

Typical Pole Height: Approximately 60 feet*
Typical Right-of-Way Width: Approximately 100 feet*

*Exact structure, height and right-of-way requirements may vary

Resources

Virtual Open House Project Fact Sheet Project Map Access Roads Field Activities

Indiana Michigan Power serves 575,000 customers in Indiana and Michigan.

www.IndianaMichiganPower.com

Eric Giffey

Project Outreach Specialist
614-736-8971
eagiffey@aep.com

* Required field. By clicking submit, you agree to AEP's Privacy Policy.

Paper plane

Your message has been sent! We'll be in touch shortly.